Local Schools District Facility Master Plan |
| |
|
•Construct
new high school (9-12)
|
-180,080
sq. ft.
-includes
purchase of land & auditorium
|
$22,976,205 |
|
•Elda
Elementary School (PreK-5)
|
-Renovation: 42,751 sq. ft. |
$4,220,198 |
|
-Addition: 14,607 sq. ft.
|
$1,898,180 |
•Morgan
Elementary School (PreK-5)
|
-Renovation:
47,050 sq. ft.
|
$4,515,844 |
-Addition:
10,365 sq. ft.
|
•Ross Middle
School (6-8)
|
-Renovation:
101,279 sq. ft.
|
$10,439,283 |
-Addition:
9,765 sq. ft.
|
•New Elementary
School (PreK-5)
|
-57,261 sq. ft.
|
$8,283,985 |
Total
Projected Costs for the Facility Project |
Total: |
$52,333,695 |
District Share: |
$28,470,162 |
State Share: |
$23,863,533 |
Facilities Plan Phases
|