| New High School (180,080 sq. ft.) |
$22,976,205 |
| Elda Addition (14,607 sq. ft.) |
$1,898,180 |
Total: |
$24,874,385 |
2002-2003 |
-Pass 6.25 Mill Bond Issue
-Begin Design Process for the New High School
-Begin Design Process for Elda additions
|
2003-2005 |
-Complete all design work
-Secure bids
-Begin construction on new high school and Elda addition
|
2005-2006 |
-Open new high school
-Move middle school students into current high school
-Begin using new addition at Elda Elementary School
-Monitor enrollment and confirm the need to construct a third
elementary school. |