Ross Local School District Facility Master Plan
PHASE ONE Construct new high school (9-12) -180,080 sq. ft. -includes purchase of land & auditorium |
$26,181,132 | PHASE TWO - SEGMENT ONE Elda Elementary School (PreK-4) -Renovation: 42,751 sq. ft. -Addition: 14,607 sq. ft.
Ross Middle School (5-8) -Renovation: 101,279 sq. ft. -Addition: 9,765 sq. ft.
|
$20,502,968 | PHASE TWO - SEGMENT TWO Morgan Elementary School (PreK-4) -Renovation: 46,440 sq. ft. -Addition: 7,165 sq. ft.
|
$9,962,291 |
|
|
|
|
| Total Projected Costs for the Facility Project
| Total: | $56,646,391 | | District Share: | $29,456,123 | | State Share: | $27,190,268 |
Facilities Plan Phases |
|