Facilities Plan Phase One

New High School (180,080 sq. ft.)

Elda Addition (14,607 sq. ft.)

All work locally funded in the amount of $26,181,132


2002-2003
-Pass 6.25 Mill Bond Issue to fund Phase One
-Begin Design Process for the New High School
-Begin Design Process for Elda Elementary additions

2003-2005
-Complete all design work
-Secure bids
-Complete construction on new high school and Elda Elementary additions

                                                  2005
-Open new high school
-Move middle school students into current high school
-Begin using new additions at Elda Elementary School

                                            2005-2009
-Monitor enrollment